Antares Xpansion
Investment simulations for Antares studies
|
!!! note "Role of this documentation"
This documentation corresponds to the technical documentation of Antares Xpansion: [input](./reference/inputs/index.md) and [output](./reference/inputs/index.md) file formats, developer guide, complete [changelog](./overview/CHANGELOG.md)... Check out the [Antares user documentation][readthedocs-antares] for more insights on Antares.
The Antares Xpansion package, works along with RTE's adequacy software Antares that is also hosted on github. Antares Xpansion aims at performing investment simulations for Antares studies.
Antares Xpansion optimizes the investments on new capacities and transmission lines for an Antares study. Typical uses of Antares Xpansion are for example:
!!! info "Goal of Antares Xpansion"
Antares Xpansion optimizes the _investments_ in order to minimize the global cost, which is the sum of the **expected operation cost during one year** and the **investment annuity**.
In an Antares study, the user builds a power system with a network of zones characterised by power plants (with their constraints e.g. max power and costs), power consumption and power transfer between zones (with the import-export transfer capacity and costs).
Antares performs probabilistic simulations of the system throughout many year-long scenarios made of 8760 hourly time frames each. The goal of the Antares simulation is to minimize the expected operation cost during one year.
Given an Antares simulation the user can define some investment candidates in the power network in order to:
Each investment candidate can potentially decrease the variable operational cost of the power system, but induces an additional investment annuity that includes:
Antares Xpansion is currently under development. Feel free to submit any issue or contribute to the documentation.